Terminology traps between the English and French codes
Start with a free official glossary: in the CNB, the defined terms in Division A, Article 1.4.1.2 (from page 1-4) print the English term in brackets after each French one, for example Premier étage (first storey). These are the traps that matter most.
| English term | CNB or CNÉB term | Why it trips people |
| occupancy | usage | The CNB classifies buildings by usage; occupation is not its word |
| exit, access to exit | issue, accès à l'issue | Everyday French says sortie; the Code says issue |
| fire block | pare-feu | In everyday French a pare-feu is a firewall. In the CNB it seals a concealed space, and a firewall is a mur coupe-feu |
| fire-resistance rating, fire-protection rating | degré de résistance au feu, degré pare-flammes | The same trap as in English: assemblies get one, closures get the other |
| first storey | premier étage | Defined as the uppermost storey with its floor no more than 2 m above grade, which is not always the floor people call the premier étage in everyday speech |
| limiting distance, exposing building face, unprotected opening | distance limitative, façade de rayonnement, baie non protégée | All three meet in Subsections 3.2.3 and 9.10.14 |
| occupant load | nombre de personnes | The French term counts people; there is no charge in it |
| alternative solution (NBC) | solution de rechange | Objective 5.4 in the French Guide uses this term (p. 17) |
| trade-off path (NECB) | solutions de remplacement | Looks interchangeable with rechange, but it is the NECB compliance path, not an NBC alternative solution |
| FDWR, HDD | FDWR, HDD | The CNÉB keeps the English abbreviations |
The rechange and remplacement pair deserves a second look. Article 1.1.2.1 of the CNÉB, Division B, sets out the compliance routes: prescriptive requirements or solutions de remplacement (the trade-off path) in Parts 3 to 7, and the performance paths in Parts 8 and 10. An NBC alternative solution, covered in our alternative solutions study notes, is a different mechanism under Division A.
CCDC 2 terms for Section 4
The French Guide's own sample for objective 10.1.1 asks who prepares a directive de modification under CCDC 2 (p. 29). These terms from the CCDC's French table of contents for Contrat à forfait differ most from a literal translation; our CCDC 2 vs RAIC Document 6 guide covers the contracts themselves.
| CCDC 2 (English) | CCDC 2 (French) |
| Consultant | Professionnel |
| Owner | Maître de l'ouvrage |
| GC 6.2 Change Order | CG 6.2 Avenant de modification |
| GC 6.3 Change Directive | CG 6.3 Directive de modification |
| Supplemental Instruction | Instruction supplémentaire |
| Substantial Performance of the Work | Achèvement substantiel de l'ouvrage |
| GC 12.1 Ready-for-Takeover | CG 12.1 Prêt pour l'occupation |
| GC 2.3 Review and Inspection of the Work | CG 2.3 Surveillance et inspection de l'ouvrage |
Watch the last row. The French CG 2.3 uses surveillance for the Consultant's review, while the Contractor's supervision is GC 3.5 in both languages. Translating surveillance back as "supervision" puts the architect in charge of the Contractor's work, which is the wrong answer on a responsibility question.