Site reviews and field review reports
GC 2.2.2 has the Consultant visit the site "at intervals appropriate to the progress of construction" to determine whether the Work is in general conformity with the Contract Documents. CHOP Chapter 6.6 treats general review, field review, site review and site observations as one service, and says supervision belongs to the contractor while inspection, a close examination of the work, is beyond the architect's normal responsibilities. It even advises writing "review," not "inspect" or "supervise," in all documentation.
Frequency is the architect's judgment, but CHOP's guidelines make good exam material: at start-up and excavation, at the start of the enclosure trades and the finishing trades, before and during concrete placement, before work such as insulation, firestopping and vapour barriers is covered up, and after severe or unexpected weather.
CHOP says to write a report after every visit. Typical contents include who reviewed, the date and weather, who was present, percentage complete by trade, progress against the schedule, questions raised, determinations made, outstanding issues and the distribution list. Objective 10.3.3 names this report directly.
For objective 11.1.4, CHOP's summary of inspection and testing firms: they do not supersede the architect's authority, they report but do not interpret results or instruct the contractor, and the owner generally pays, often through a cash allowance. When work is opened up, GC 2.3.5 puts the cost on whoever was wrong: the Contractor if it does not conform, the Owner if it does.