Schedules: CPM, float, milestones, and delay
Schedules are the smallest of the three patterns but the one Intern Architects most often skip because the topic feels like a project manager problem, not an architect problem. Section 4 tests schedules because the architect administers the contract time under CCDC 2 GC 1.1 and is the party that certifies substantial performance, which is itself a date driven by the schedule.
What CPM logic the exam expects
A typical Section 4 schedule question presents either a CPM network (nodes and arrows with durations) or a milestone log (activities, durations, predecessors) and asks one of a small set of things. Identify the critical path. Calculate total float for a named activity. Decide whether a named delay extends the substantial-performance date. Decide whether a named delay is excusable, compensable, both, or neither under CCDC 2 GC 6.5.
The CPM skills the exam expects are basic: early start, early finish, late start, late finish, total float (late minus early), and the critical path (the longest duration chain through the network, which has zero total float). Free float (the time an activity can slip without delaying its successor) appears occasionally in distractors. The exam does not test resource levelling, monte carlo, or earned-value analysis.
Delay analysis the exam expects
Under CCDC 2 GC 6.5, a delay is excusable if it is caused by an event outside the contractor's control and the contractor gives timely written notice. An excusable delay extends the contract time. A delay is compensable only when CCDC 2 specifically provides for compensation (for example, owner-caused delays, or delays caused by changes the owner directs). Most weather delays are excusable but not compensable; a strike is typically excusable but not compensable; an owner-caused redesign is both. Candidates lose marks when they assume every excusable delay is also compensable.
Schedule study strategy
Two evenings of focused practice is typically enough to lock in the schedule pattern. Read CHOP Chapter 5.1 once, then drill 20 to 30 CPM and delay questions under timed conditions. If a question stumps you, redraw the network and walk the path; CPM is a visual problem the moment you draw it. Do not try to memorise the activity counts in the practice problems; the exam will use different activity sets.