References

The books behind these questions.

Every Schematic Design practice question links back to the reference you would use in the real exam.

CHING

Building Construction Illustrated. Pages 1.13 to 1.44 cover site analysis inputs; pages 2.02 to 2.40 cover whole-building systems and structural concepts; Appendix A.23 summarises the Uniformat II elemental format used to structure schematic cost estimates.

CHOP

Canadian Handbook of Practice. Chapter 6.2 describes the schematic design process in sequence: what the architect does, what the consultants deliver, and what constitutes client approval to proceed.

Heating, Cooling, Lighting

4th Edition. Chapter 1 covers climate-responsive design principles for concept decisions; Chapter 19 covers daylighting rules of thumb for window sizing and placement at the schematic stage.

The Architect's Studio Companion

6th Edition. Sections 1 to 4 give structural and mechanical system rules of thumb that translate directly into schematic design decisions and span selection for common building types.

What you'll be tested on

The skills behind Schematic Design questions.

Examitect drills each of these areas. The list below maps to the question categories you will see inside.

  • Read site conditions and translate them into concept constraints and opportunities
  • Develop a building concept: massing, parti, building organisation pattern, and structural grid
  • Select a structural system family using span and floor-to-floor height rules of thumb
  • Apply passive design strategies and coordinate mechanical and electrical inputs at the schematic stage
  • Prepare a Class C or D cost estimate and confirm the concept is feasible within the project budget
  • Produce the SD drawing set and obtain client approval to proceed to design development

Why this topic matters. Schematic Design questions test whether you can move from program to concept without losing track of code, budget, or client goals. The examiners reward candidates who treat the schematic phase as a decision phase, not a drawing phase. Choices made here lock in roughly 70 percent of the final project cost, so every concept decision carries real weight.

Study Notes on Schematic Design.

The schematic design phase

Schematic design is where program becomes form. You take the approved brief from the programming phase and produce a concept the client can visualise, react to, and ultimately sign off on. The product is not a set of construction documents: it is a set of decisions that define the building's fundamental character.

Decisions made at the schematic stage are the most consequential in the project. Studies of project cost show that roughly 70 percent of the final project cost is committed by the end of schematic design, when total fees spent are typically less than 15 percent of the budget. Changing the structural system or the massing at design development costs far more than changing it now.

PhaseKey outputCost committed
ProgrammingApproved architectural program~5%
Schematic DesignClient-approved concept package~70%
Design DevelopmentCoordinated DD drawings~85%
Construction DocumentsPermit-ready drawing set~95%
Construction AdministrationCompleted building100%

Examitect's ExAC study plan addresses Schematic Design in one sub-category. Click the jump button below to go directly to the sub-category notes.

Sub-categoryPrimary references
6.1 Understand aspects of schematic design Jump to sub-category 6.1 CHING 1.13-1.44, 2.02-2.40, App. A.23; CHOP Ch. 6.2

What enters and exits the schematic design phase

Understanding the phase boundary is itself an ExAC topic. Questions often ask what the architect needs before starting SD, what decisions get made during it, and what the client must approve before DD begins.

SD inputsSource
Signed-off architectural programProgramming phase; client-approved
Signed professional services agreementOwner; required before design work begins
Site survey and legal descriptionSurveyor; defines property lines, easements, setbacks
Geotechnical reportGeotechnical engineer; defines soil bearing and foundation options
Zoning and planning reviewMunicipality; confirms permitted use, height, density
Utility servicing informationUtility companies; water, sewer, electrical capacity
SD vs. DD: what gets decided whereSDDD
Massing and building footprintEstablishedRefined
Structural system familySelectedSized and specified
Core and circulation layoutLocatedDimensioned
HVAC system typeChosenDesigned
Exterior envelope materialNot yet selectedSelected and specified
Door and hardware schedulesNot applicableProduced
Cost estimateClass C or D (elemental)Class B (detailed elemental)
Exam tip

If a question asks whether an action is appropriate "at the schematic stage," check whether it involves setting the concept or refining the details. Concept-setting belongs in SD; detail refinement belongs in DD. Selecting a specific exterior cladding material, for example, is a DD decision, not an SD decision.

6.1 Understand aspects of schematic design

This sub-category covers the full arc of the schematic phase, from the first site visit through to the client-approved SD package. It is the only sub-category for Schematic Design in Examitect's ExAC study plan, so all questions in this topic map back to one or more of the six aspects below.

AspectWhat it involvesKey reference
Site conditionsReading topography, solar angles, wind, views, legal constraints, and servicing to generate concept opportunities and constraintsCHING 1.13-1.44
Concept and massingDeveloping the parti, testing organisation patterns against the program, and producing massing options the client can compareCHING 2.02-2.40; CHOP Ch. 6.2
Structural system selectionChoosing a structural system family based on program bay requirements, floor-to-floor targets, and budget; using span rules of thumb to confirm feasibilityStudio Companion Sec. 1-2
Environmental designApplying passive strategies (orientation, shading, thermal mass, natural ventilation) and sizing major glazing areas for daylightingHCL Ch. 1, 19; Studio Companion Sec. 3
Engineering coordinationDirecting consultants to confirm system types, locate shafts and equipment rooms, and confirm service capacities before SD submissionCHOP Ch. 6.2; Studio Companion Sec. 4
SD deliverablesProducing the drawing set, outline specification, preliminary code analysis, and Class C or D cost estimate; presenting to the client and obtaining sign-off to proceed to DDCHOP Ch. 6.2

Site analysis at the schematic stage

CHING pages 1.13 to 1.44 cover the information an architect reads from a site and how each factor shapes early design decisions. At the schematic stage you are not just documenting site data: you are translating it into constraints the concept must respect and opportunities the concept should exploit.

Site factorData sourceDesign implication
Solar anglesSun-path diagram (latitude-specific)Orient the long building axis east-west; shade south-facing glazing with horizontal overhangs; limit west-facing glass to control afternoon heat gain
Prevailing windsClimate data, wind roseLocate operable windows on the leeward face for natural ventilation; position mechanical intakes upwind of exhaust outlets
Topography and drainageSite survey, contoursSet finished floor elevations above the 100-year flood plain; use grade changes to introduce daylight to lower levels
Views and privacySite visit, photographsMaximise valued views; screen service areas and loading from public streets and neighbouring residential uses
Setbacks and easementsSite plan, title search, zoning by-lawAll buildings, overhangs, and below-grade structures must clear setback lines and easement corridors
Soil bearing capacityGeotechnical reportDetermines foundation type: spread footings (good bearing), mat (poor or variable), piles (soft or contaminated soils)
Existing vegetationArborist report, surveyIdentify trees to protect under municipal by-law; factor existing canopy into summer shading analysis
Access and servicingSite plan, municipal drawingsConfirm pedestrian, vehicle, and emergency access points; locate service entry away from primary facades
Exam tip

ExAC questions on site analysis often present a scenario with a specific site constraint and ask what design response is most appropriate. The correct answer addresses the constraint directly (e.g., orienting the building, adding shading) rather than ignoring it or pushing it to a later phase. Reading CHING 1.13-1.44 carefully before the exam pays off here.

Building organisation patterns

The primary spatial organisation patterns that architects use to translate a program into a plan are catalogued in Ching's Architecture: Form, Space, and Order; the CHING primary reference, Building Construction Illustrated pages 2.02 to 2.40, complements them with whole-building systems and structural concepts. Each pattern has a characteristic form, a characteristic circulation system, and a set of program types for which it performs well. Choosing the right organisation pattern is one of the first concept decisions you make in SD.

Organisation patternForm descriptionWell-suited programs
CentralisedA dominant central space surrounded by secondary spaces oriented toward itCivic buildings, libraries, museums, atria
LinearSpaces arranged along a primary circulation spine; the spine can be straight, bent, or curvedSchools, hospitals, residential corridors, long-span industrial
RadialLinear wings radiating from a central node; combines centralised and linear characteristicsAirports, some hospitals, prisons (surveillance from centre)
ClusteredSpaces grouped by functional proximity without a strict geometric order; linked by adjacency rather than a spineVillage-scale plans, campus planning, childcare centres
GridSpaces arranged on a regular structural grid; allows flexibility and future reconfigurationOffice buildings, laboratories, research facilities, retail

The building organisation pattern you select must be consistent with the approved program. A hospital program with many identical patient rooms points toward a linear or grid organisation; a civic building program centred on a large public hall points toward a centralised organisation. ExAC questions sometimes present a program and ask you to identify the most appropriate organisation type, or present a massing and ask whether it is consistent with a given program.

Exam tip

A parti is a specific expression of the organisation pattern: it is the single governing concept that unifies the building. The parti should be expressible as a simple diagram. Questions about parti ask whether proposed changes are consistent with it, not whether the building looks a certain way.

Structural system selection

At the schematic stage you select a structural system family based on three inputs: the bay spans required by the program, the floor-to-floor heights required by the mechanical and occupancy type, and the cost target. You are not yet sizing members or specifying connections: that is design development work. Use the span rules of thumb below to confirm feasibility and eliminate incompatible systems.

Structural systemTypical bay spanFloor-to-floorCommon uses
Light wood frame3 to 6 m2.7 to 3.0 mHouses, low-rise multi-family, small commercial
Post-and-beam wood6 to 9 m3.0 to 4.0 mSmall commercial, community halls, barns
Mass timber (CLT / glulam)6 to 12 m3.5 to 4.5 mMid-rise residential, institutional, office
Steel open-web joists9 to 18 m3.5 to 4.5 mSchools, retail, light industrial, arenas
Steel wide-flange frame9 m or more3.5 to 5.0 mOffice towers, institutional, mixed-use high-rise
Concrete flat plate6 to 9 m3.0 to 3.5 mResidential, hotel (no drop panels)
Concrete flat slab8 to 12 m3.5 to 4.5 mParking structures, commercial (with drop panels)
Concrete waffle slab9 to 15 m4.0 to 5.0 mAuditoriums, laboratories, long-span institutional
Exam tip

ExAC questions on structural systems often give you a program with a specific bay requirement (e.g., 12 m column-free spans for a gymnasium) and ask which system is most appropriate. Match the required span to the table above and eliminate systems that cannot reach it. Then consider cost: wood is generally least expensive, post-tensioned concrete and steel wide-flange are more costly. The right answer usually satisfies both span and cost constraints.

Passive design strategies at the schematic stage

Heating, Cooling, Lighting Chapters 1 and 19 cover the climate-responsive design principles and daylighting rules of thumb that apply at the schematic stage. You are not running energy models: you are making concept decisions that determine whether the building will perform well or poorly before mechanical systems are even selected.

Passive strategySD decisionReference
Solar orientationAlign the long building axis within 15 to 20 degrees of true east-west to maximise south exposure for heating and minimise east and west exposure for coolingHCL Ch. 1
ShadingProvide horizontal overhangs on south glazing sized to block high summer sun and admit low winter sun; use vertical fins on east and west facadesHCL Ch. 1
Thermal massIn heating climates, use exposed concrete or masonry on interior south-facing surfaces to store solar gain and release it overnightHCL Ch. 1
Natural ventilationLocate operable openings on opposite facades to create cross-ventilation; use stack-effect strategies (atria, clerestories) to draw air through deep plansHCL Ch. 1
DaylightingTarget a window-to-floor-area ratio of 20 to 30 percent for well-daylit offices; place windows high in the wall to distribute light deeper into the floor plate; use light shelves to redirect light to the ceilingHCL Ch. 19
Glare controlAvoid placing workstations directly facing west windows; use external shading or fritted glazing on high-glare orientationsHCL Ch. 19
Exam tip

Questions about passive design at the schematic stage ask what the architect should decide now, not what the mechanical engineer will size later. If a question asks about cooling load reduction at the SD stage, the correct answers involve orientation, shading, and window-to-wall ratio, not cooling system selection or duct sizing.

Engineering consultant coordination

The architect does not produce all of the schematic design package alone. During SD you direct each engineering consultant to produce a preliminary input that you incorporate into the SD submission. The goal is to confirm that the concept is structurally feasible, that the mechanical and electrical systems fit within the floor-to-floor heights and core locations you have proposed, and that utility service capacities are adequate.

DisciplineSD deliverableKey question for the architect
StructuralPreliminary structural concept note; typical bay sketch showing system type, approximate depth, and column gridDoes the proposed structural grid support the program bay sizes and fit within the target floor-to-floor height?
Mechanical (HVAC)System type recommendation; approximate shaft and mechanical room locations; preliminary ventilation and cooling load estimateHave central shafts and penthouse or basement mechanical room locations been confirmed and reflected in the plans?
PlumbingCore location confirmation; preliminary wet area stacking diagram; pipe route from each floor to the building drainAre all wet areas stacked vertically above a clear basement pipe route to the municipal sewer?
ElectricalService entry point; approximate main switchgear room location; preliminary load estimateHas utility service capacity been confirmed for the project's estimated electrical load?
Fire protectionSprinkler and standpipe system type recommendation; preliminary water supply confirmationDoes the structural bay spacing allow standard sprinkler head coverage without additional intermediate supports?
Exam tip

ExAC questions sometimes describe a situation where a consultant has not yet confirmed a key input and ask what the architect should do. The correct answer is to obtain the confirmation before finalising the SD submission, not to proceed without it. An SD package submitted without confirmed shaft locations or structural feasibility is incomplete.

The schematic design deliverable set

CHOP Chapter 6.2 describes what the SD package contains. The drawing set is produced at a low level of detail: the goal is to communicate the concept clearly enough for the client to make an informed approval decision, not to provide information for construction.

DocumentTypical scaleContent
Site plan1:500Building footprint, setback compliance, vehicular and pedestrian access, grading concept, landscaping zones
Schematic floor plans1:200Room layout, circulation paths, core location, structural grid, gross floor area by use
Building sections1:200Floor-to-floor heights, structural system depth, roof profile, relationship to grade
Preliminary elevations1:200Massing, window proportions, main entry, relationship to adjacent buildings
Outline specificationTextStructural system family, exterior cladding material families, mechanical system type, sustainability targets
Preliminary code analysisTextOccupancy group(s), construction type, allowable height and area, exit count and locations, accessible routes
Preliminary cost estimateTextClass C or D elemental estimate; plus or minus 15 to 25 percent accuracy; total project cost and cost per gross square metre

Code analysis at the schematic stage

The preliminary code analysis is not the full code review you will complete at DD: it is a strategic check to confirm the concept is viable under the National Building Code. At minimum you confirm:

  • Major occupancy group and any secondary occupancies
  • Construction type (combustible vs. non-combustible) and whether it is consistent with the building height
  • Number of storeys and whether the building exceeds the limits for the proposed construction type
  • Minimum number of exits and whether the floor plate configuration can accommodate them
  • Whether accessible path of travel is feasible from the site to all major spaces

Preliminary cost estimation

The cost estimate is one of the most consistently tested topics in Schematic Design questions. At SD you produce a Class C or D estimate to confirm the concept is feasible within the client's budget. If the estimate exceeds the budget, you adjust the concept now, when changes are inexpensive, rather than at DD or CD stage.

Estimate classAccuracyBasisUsed when
D (Conceptual)±25 to 40%Total cost per gross square metre of building typeFeasibility study; programming phase budget confirmation
C (Schematic)±15 to 25%Elemental cost per square metre by building element (structure, envelope, interiors, mechanical, electrical, sitework)SD approval; client budget confirmation before DD begins
B (Design development)±10 to 15%Detailed elemental with quantities and unit pricesDD approval; financing applications
A (Tender)±5 to 10%Unit prices from trade breakdowns; contractor-confirmedTender and contract award

Elemental cost format

A Class C estimate breaks the project cost into major elements rather than trade divisions. Common elements include: substructure (foundations), structure (floor and roof systems), exterior enclosure (walls, windows, roof membrane), interior construction (partitions, finishes, doors), mechanical systems, electrical systems, and site works. Each element is estimated as a cost per square metre of building area multiplied by the gross floor area. This elemental structure follows the Uniformat II classification summarised in CHING Appendix A.23.

Exam tip

RSMeans and Yardsticks for Costing are the primary Canadian sources for unit cost data. Both are open-book references on the ExAC. Questions about cost estimation at SD ask about the process and the appropriate accuracy range, not about memorising specific dollar values.

Key terms and reference guide

The glossary below covers the terms most often tested in Schematic Design questions. The reference guide that follows tells you which source to consult for each type of question.

Parti
The single governing concept from which all major design decisions flow; expressible as a simple diagram; the "big idea" of the project.
Schematic design
The project phase in which the approved program is translated into a concept: massing, organisation, structural system, and a cost estimate the client can approve.
Design development
The phase following SD in which the approved concept is refined: materials are selected, dimensions are fixed, and engineering systems are designed in detail.
Elemental estimate
A cost estimate that organises project costs by building element (structure, envelope, mechanical, etc.) rather than by trade or specification division.
Class C estimate
An elemental estimate with accuracy of plus or minus 15 to 25 percent; the standard format for cost confirmation at the SD stage.
Organisation pattern
The spatial strategy that relates rooms and spaces to each other: centralised, linear, radial, clustered, or grid.
Structural grid
The regular layout of columns or bearing walls that defines the structural bays; established at SD, refined at DD.
Bay span
The centre-to-centre distance between columns or bearing walls in one direction; the primary driver of structural system selection.
Floor-to-floor height
The distance from finished floor to finished floor on the storey above; must accommodate structural depth, mechanical zone, and occupied ceiling height.
Passive design
Building design strategies that reduce energy demand without mechanical intervention: orientation, shading, thermal mass, natural ventilation, and daylighting.
Question typePrimary referencePages or sections
Site analysis and constraintsCHING1.13-1.44
Building organisation and massingCHING2.02-2.40
Structural system selectionStudio CompanionSec. 1-2
SD process and deliverablesCHOPCh. 6.2
Passive design and solar strategyHCLCh. 1
DaylightingHCLCh. 19
Mechanical system type selectionStudio CompanionSec. 3-4
Cost estimation method and accuracyCHING; RSMeans; Yardsticks for CostingApp. A.23 (Uniformat II); Introduction sections

ExAC question patterns and strategies

Schematic Design questions follow recognisable patterns. Knowing the patterns helps you identify the correct answer quickly and avoid the distractors the examiners build in.

Common question types

  • Phase boundary questions. A scenario describes an action and asks whether it is appropriate "at the schematic stage." Check whether the action involves concept-setting (SD) or detail refinement (DD).
  • Structural system selection. A program gives you required bay spans and asks which system is most appropriate. Match span to the table in Card 7; eliminate systems that cannot reach the required span.
  • Site constraint response. A site condition is described (steep grade, prevailing wind, south-facing adjacent building) and the question asks what design response is most appropriate at SD.
  • Deliverable identification. A question asks what document belongs in the SD submission. Know the seven items in the SD deliverable set from Card 10.
  • Cost estimate accuracy. A question asks which estimate class is appropriate at a given project stage, or what the accuracy range of a Class C estimate is.
  • Engineering input timing. A question asks when a specific consultant input is required. Structural feasibility, shaft locations, and utility capacity confirmations all belong in the SD phase.

Common distractors

  • Answers that push SD decisions into DD (e.g., "defer structural system selection until DD") are almost always wrong; the structural system must be confirmed at SD.
  • Answers that push DD details into SD (e.g., "select the exterior cladding material") are also wrong; material selection belongs in DD.
  • Cost estimate answers that overstate accuracy (e.g., "plus or minus 5 percent") are wrong for the SD stage; plus or minus 15 to 25 percent is correct for a Class C estimate.
  • Passive design answers that require mechanical intervention are wrong when the question asks about passive strategies specifically.
Exam tip

The single most effective strategy for SD questions is to ask: is this a concept decision or a detail decision? If it is a concept decision and the question is set at the SD stage, the action is appropriate. If it is a detail decision, it belongs in DD. This filter eliminates the majority of distractors.

Estimated study time. Most candidates spend 8 to 12 hours on Schematic Design. Adjust upward if you have not done schematic-stage work in your day job, and focus the extra time on structural system selection and cost estimation: these are the areas most often tested. If you regularly lead SD phases in practice, a focused 6-hour pass through the references may be enough.

FAQ

Schematic Design FAQ

Schematic design is the phase where you translate an approved architectural program into a building concept. Sub-category 6.1 tests your ability to establish massing, structural grid, engineering system concept, and a preliminary cost estimate the client can approve before moving into design development.

Sub-category 6.1, Understand aspects of schematic design, covers the full schematic phase: reading site conditions, developing concept options, selecting structural and engineering systems, preparing the SD drawing set, and obtaining client approval to proceed to design development.

Schematic design establishes the concept: massing, structural system, and approximate cost. Design development refines that concept: materials, detailed dimensions, system performance, and coordinated drawings. ExAC questions test the boundary between the two phases, so know which decisions belong in each.

The standard SD set includes a site plan, schematic floor plans at 1:200 or 1:500, building sections, preliminary elevations, an outline structural and mechanical narrative, and a Class C or D cost estimate. A basic code analysis confirms occupancy classification, exits, and accessible routes.

A parti is the single governing concept from which all major design decisions flow. ExAC questions about parti test whether you can identify the organising idea behind a building and evaluate whether proposed changes are consistent with it.

At the schematic stage you are choosing a system family, not specifying member sizes. Key spans: light wood frame 3 to 6 m, post-and-beam wood 6 to 9 m, mass timber 6 to 12 m, steel open-web joists 9 to 18 m, steel wide-flange 9 m or more, concrete flat plate 6 to 9 m, concrete flat slab 8 to 12 m.

Primary references are CHING Building Construction Illustrated pages 1.13 to 1.44 (site analysis) and 2.02 to 2.40 (building systems and structural concepts), and CHOP Chapter 6.2 (process and deliverables). Supplementary references are Heating, Cooling, Lighting 4th Edition Chapters 1 and 19, and The Architect's Studio Companion 6th Edition Sections 1 to 4.

Use an elemental estimate expressed in dollars per square metre for each major building element, with accuracy of plus or minus 15 to 25 percent. RSMeans and Yardsticks for Costing are the standard Canadian sources for unit costs. At SD you are confirming the project is feasible within budget, not producing a tender-ready number.

Building orientation, window placement and sizing, shading devices, thermal mass, and natural ventilation paths. Heating, Cooling, Lighting Chapter 1 covers climate-responsive design principles and Chapter 19 covers daylighting. At SD you are choosing passive strategies and sizing major glazing areas, not running detailed energy calculations.

At SD you confirm occupancy classification, calculate allowable height and area, determine the number and location of exits, and identify accessible routes. You are not yet selecting door hardware or fire-stopping details. The goal is to confirm the concept is code-compliant before committing resources to detailed design.

Most candidates spend 8 to 12 hours on this topic. Focus extra time on structural system selection and cost estimation, which are the areas most often tested. If you have done significant SD work in practice, a focused review of the references may be enough.

CHING provides the visual and technical side: site analysis overlays, whole-building system diagrams, and the Uniformat II elemental cost format in Appendix A.23. Structural span rules of thumb come from The Architect's Studio Companion, and the classic organisation typologies come from Ching's Architecture: Form, Space, and Order. CHOP Chapter 6.2 focuses on process: what the architect does, in what order, and what the deliverables are. Use CHING when you need to evaluate a concept option, and CHOP when you need to trace a document back to its phase.